Site Survey
For the period 08_11 January 2018, several sessions of Site Surveys have been conducted to select the best locations for the WAM ground stations.
System Design
- Distributed clock architecture.
- Eight (8) Ground Stations (GS)
- Five (5) Receiving Stations (RX),
- One (1) is Receiving / Transmitting Station (RXTX)
- Two (2) are Receiving / Transmitting Stations (RXTX) with communication node.
- Central Processing Station (CPS) – Dual CPS is the heart of the system and performs multilateration calculation, target, data and system management.
- Automation system (ERIS)
- Control Room – Seven (7) CWPs
- Microwave links.
Factory Training
- SIA technical staff
- SIA ATC controllers staff
- WAYPOINT installation team
FAT
Factory Acceptance Test – 2 inspectors – 18 June 2018
Packing & Shipping
Installation
- Done by WAYPOINT Staff
- Installation kick off: 28 August 2018
- Installation complete: 15 October 2018
- Working days duration: Forty (40) days
Adaptation & Configuration
SAT
04 – 06 December 2018
Warranty
One year 06 Dec. 2018 _ 05 Dec. 2019
Flight Check
- Commissioning date: : 2019-02-20 8:11:50 UTC
- Test aircraft: Diamond DA42
- Mode S address: 405D6E
- Mode A: 1310
- Callsign: DCT06
- Flight level: 130