PROJECT SCHEDULE

Site Survey

For the period 08_11 January 2018, several sessions of Site Surveys have been conducted to select the best locations for the WAM ground stations.

System Design

  • Distributed clock architecture.
  • Eight (8) Ground Stations (GS)
  • Five (5) Receiving Stations (RX),
  • One (1) is Receiving / Transmitting Station (RXTX)
  • Two (2) are Receiving / Transmitting Stations (RXTX) with communication node.
  • Central Processing Station (CPS) – Dual CPS is the heart of the system and performs multilateration calculation, target, data and system management.
  • Automation system (ERIS)
  • Control Room – Seven (7) CWPs
  • Microwave links.

Factory Training

  • SIA technical staff
  • SIA ATC controllers staff
  • WAYPOINT installation team

FAT

Factory Acceptance Test – 2 inspectors – 18 June 2018

Packing & Shipping

Installation

  • Done by WAYPOINT Staff
  • Installation kick off: 28 August 2018
  • Installation complete: 15 October 2018
  • Working days duration: Forty (40) days

Adaptation & Configuration

SAT

04 – 06 December 2018

Warranty

One year 06 Dec. 2018 _ 05 Dec. 2019

Flight Check

  • Commissioning date: : 2019-02-20 8:11:50 UTC
  • Test aircraft: Diamond DA42
  • Mode S address: 405D6E
  • Mode A: 1310
  • Callsign: DCT06
  • Flight level: 130